Industrial Real Estate
CBRE reported 1.7 million square feet of positive net absorption in Kansas City in the second quarter, with vacancy at 4.5%. Of more than 1.4 million square feet delivered, 960,000 square feet was build-to-suit and 460,000 square feet was speculative. [1] The mix is useful: broad demand is supportive, but a project’s value still depends on its tenant path, building readiness, and submarket-specific competition. Overall asking rents were down year over year, reinforcing the case for underwriting execution rather than relying on headline growth.
Energy and Mission-Critical Infrastructure
Evergy said its 2026 integrated-resource-plan preference includes more than 5 gigawatts of additions through 2032 and that it expects about $1 billion of incremental capital tied to resources needed for secured customer agreements. [2] These are system-planning and capital signals, not confirmation of capacity at any specific site. The investable follow-up is still written evidence on service timing, upgrade scope, cost responsibility, interconnection, and regulatory milestones.
Infrastructure Delivery
MoDOT’s Improve I-70 Kansas City program continues field work, including September earthwork and drainage activity near 23rd Street and bridge work near 18th Street. [3] Separately, Kansas City reports ongoing water, sewer, street, and alley improvements in the West Bottoms, with Phase 1 public-realm work expected to finish in November. [4] Neither update is a proxy for site readiness elsewhere; together, they illustrate why access, utility sequencing, and construction interfaces belong early in feasibility work.
Nazir Ventures View
Prioritize evidence that turns a market thesis into a deliverable asset. This week’s checklist:
- Test industrial demand with tenant, delivery, and submarket evidence—not market totals alone.
- Confirm the utility path in writing before assigning value to planned generation or contracted load.
- Map public-work and construction interfaces against the project schedule, access plan, and approvals.
Sources
Public sources reviewed October 5, 2026; reporting periods and project schedules may change.